The item that provides more detailed descriptions of the components in the work breakdown structure seenagape 12 years ago The item that provides more detailed descriptions of the components in the work breakdownstructure (WB5) is called a WBS: A.dictionary. B.chart. C.report. D.register. ← Previous question Next question →