PMI Exam Questions

The engagement level of the stakeholders should be classified as:

The project manager notes that stakeholders are aware of the project and potential impacts and
are actively engaged in ensuring that the project is a success. The engagement level of the
stakeholders should be classified as:

A.
Supportive

B.
Leading

C.
Neutral

D.
Resistant