The correct equation for schedule variance (SV) is earn…

The correct equation for schedule variance (SV) is earned value:

A.
minus planned value [EV – PV].

B.
minus actual cost [EV – AC].

C.
divided by planned value [EV/PV],

D.
divided by actual cost [EV/AC].