The activity that is most concerned with the current status of the project schedule is called ______

The activity that is most concerned with the current status of the project schedule is called ___________.

A.
Project time management

B.
Control Schedule

C.
Monitoring and controlling

D.
All of the above

Explanation:
Control Schedule: The activity that is most concerned with the current status of the project schedule.