PMI Exam Questions

SOW is not listed as one of the inputs to Collect Requirements in PMBOK.

A is the correct answer. product scope is measured against WBS and WBS Dictionary. The planned work contained within the lowest-level WBS components, which are called work packages, can be scheduled, cost estimated, monitored, and controlled. SOW is not listed as one of the inputs to Collect Requirements in PMBOK.

A.
Functional

B.
Weak matrix

C.
Project coordinator

D.
Project expediter