PMI Exam Questions

Parametric Estimate Costs involves:

Parametric Estimate Costs involves:

A.
Calculating individual cost estimates for each work package

B.
Using rates and factors based on historical experience to estimate costs

C.
Using the actual cost of a similar project to estimate total project costs

D.
Both A and B