Most changes requests are a result of ___________

Most changes requests are a result of ___________

A.
Value added change (Enhancements)

B.
Schedule constraints

C.
Regulatory constraints

D.
Improvement to the project scope

Explanation:
Most change requests (CRs) are a result of Value added change (Ennhancements)