PMI Exam Questions

Information collected on the status of project activities being performed to accomplish the project

Information collected on the status of project activities being performed to accomplish the project
work is known as what?

A.
Project management information system

B.
Work performance information

C.
Work breakdown structure

D.
Variance analysis