PMI Exam Questions

In which phase project manager is assigned to a project?

In which phase project manager is assigned to a project?

A.
During the initiation stage

B.
During the planning stage

C.
After approval of budget

D.
After the project is proven feasible

Explanation:
output of Initiation process : Project charter PM assigned Constraints Assumptions Project manager is assigned to a project During the initiation stage.