In this situation, you should take all of the following steps EXCEPT:

You are the project manager and cost or schedule for a project is often dictated by management. In this situation, you should take all of the following steps EXCEPT:

A.
Accept is with no prior action.

B.
Inform management of the consequences.

C.
Negotiate scope.

D.
Perform risk assessment.