PMI Exam Questions

In a project selection model, the most important factor is which one of the following?

You are a project manager and the management wants you to help them determine which projects should be selected for implementation. In a project selection model, the most important factor is which one of the following?

A.
Business needs

B.
Type of constraints

C.
Budget

D.
Schedule

Explanation:
Projects are selected based on business needs first.