During ___________ project management process, stakeholder’s ability to influence project resu

During ___________ project management process, stakeholder’s ability to influence project results is high?

A.
Initiating

B.
Planning

C.
Monitoring and Controlling

D.
Executing

Explanation:
The Initiating process is where stakeholders have the greatest ability to influence outcomes of the project. Risk is highest during this stage because of the high degree of unknown factors.