PMI Exam Questions

Cost benefit analysis, score card modelling, paybacks periods, and internal rate of return are examp

Cost benefit analysis, score card modelling, paybacks periods, and internal rate of return are examples of:

A.
Enterprise benefits measurements methods when selecting a project

B.
Integarl parts of the SOW

C.
Ways to ensure stakeholders commitment

D.
Project selection methods

Explanation:
Projects are seeded from the recognition of a regulatory or bussines need.