Which of the following outputs from the Control Schedule process aids in the communication of schedu

Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance inde

x (SPI), or any performance status to stakeholders?

A.Performance organizations

B.Schedule baselines

C.Work performance measurements

D.Change requests