A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should&#82

A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should

be the concern?

A.There is a cost underrun.

B.There is a cost overrun.

C.The project may not meet the deadline.

D.The project is 20 days behind schedule.