A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should
be the concern?
A.There is a cost underrun.
B.There is a cost overrun.
C.The project may not meet the deadline.
D.The project is 20 days behind schedule.