Based on the following metrics EV $20,000, AC $22,000 and PV $ 28,000 what is the project CV seenagape 12 years ago Based on the following metrics EV $20,000, AC $22,000 and PV $ 28,000 what is the project CV. A.-$8,000 B.-$2,000 C.$2,000 D.$8,000 ← Previous question Next question →