At which stage, stakeholders have the maximum influence on a project?

At which stage, stakeholders have the maximum influence on a project?

A.
Initial stage

B.
Closing stage

C.
Execution stage

D.
None of the above

Explanation:
It is easy to make changes to project goals and approach at the initial stage. Stake holders have maximum influence at Initial stage.