PMI Exam Questions

As a project manager, you know that the most important activity to ensure customer and stakeholder s

As a project manager, you know that the most important activity to ensure customer and stakeholder satisfaction is:

A.
Documenting and meeting the requirements

B.
Reporting project status regularly and in a timely manner

C.
Documenting and meeting the performance measurements

D.
Reporting changes and updating the project plan and other project documents where appropriate

Explanation:
Documenting the requirements and meeting them is one of the key things you can do to ensure customer satisfaction