A resource Leveling is a technique for:
A.
Estimate Activity Durations
B.
Develop schedule
C.
Estimate Activity resources
D.
Sequence Activities
Explanation:
Resource levelingHelps in utilising resources consistently throughout the project. Ensures resources are not over allocated. Helps the project manager avoid delays caused by bad allocations. Helps the project manager identify and take advantage of unused times by analysing task dependencies. MSP can automatically level resources based on resource calendar, task types, dependencies, and constraints, however, I have yet to find a project manager that has felt comfortable with the way MSP does it. I level resources manually via the Resource Usage view, but if you insist in using the automatic feature of MSP, save a copy first. If you find resource conflicts (over or under allocations) you could:
* Delay certain tasks.
* Assign a different resource.
* Change task dependencies.
* Remove tasks.
* Add tasks (instead of using the MSP’s split task functionality, which is not supported by some project management systems i.e. Clarity).