A Project Cost Management Plan is created as a part of:
A.
Estimate Costs process
B.
Determine Budget process
C.
Control Costs process
D.
None
Explanation:
Cost management plan : Describes how cost variances will be managed and Part of the overall project plan.
Output of Estimate Costs process is : Cost estimates and Cost management plan