A logical relationship in which a successor activity cannot start until a predecessor activity has f

A logical relationship in which a successor activity cannot start until a predecessor activity has
finished is known as:

A.
Start-to-start (SS).

B.
Start-to-finish (SF).

C.
Finish-to-start (FS).

D.
Finish-to-finish (FF).