PMI Exam Questions

A key barrier to team development is ______________.

A key barrier to team development is ______________.

A.
A strong matrix management structure

B.
Major problems delay the project completion date or budget targets

C.
Team members are accountable to both functional and project managers

D.
Formal training plans cannot be implemented