PMI Exam Questions

_______________ must be measured regularly to identify variance from the plan.

_______________ must be measured regularly to identify variance from the plan.

A.
Project performance

B.
Stakeholder requirements

C.
Schedule progress

D.
Cost and schedule

Explanation:
Variance Analysis: Project performance measurements are used to assess the magnitude of variation.