What Is providing detailed plans for tasks that are about to start in the near future using the most

___________________ Is providing detailed plans for tasks that are about to start in the near future using the most current information and revisting future activities when they near their starting dates

A.
Rolling wave planning

B.
Progresive elaboration

C.
Milestone detail planning

D.
Expert judgemnet