HP Exam Questions

How many nodes are needed to fulfill this requirement?

A customer has two data centers and needs 3.2TB of space in his P4300 environment. Data
should be mirrored across both data centers. How many nodes are needed to fulfill this
requirement?

A.
2 nodes

B.
3 nodes

C.
4 nodes

D.
6 nodes

Explanation: