which factor needs to be considered?

Refer to the Exhibit:
The customer wants to implement an HP StoreOnce solution for the environment shown.
You have been given the following information:
– Each branch office has approximately 100 GB of data.
– Philadelphia has approximately 2 TB data.
– Pittsburg has approximately 1 TB data.
– All backup data will be replicated back to the data center in Pittsburg.
– Costs should be kept to a minimum but allow for the possibility of adding three more sites.
When designing the solution, which factor needs to be considered?

Which components do you propose to change to meet their budget goals without sacrificing their critical to qua

A small service provider customer is in the process of a merger and needs to purchase additional

IT infrastructure components to support the expansion of their customer base. The goal is to offer
same-day repair from any hardware failures and increased high availability from the servers to the
local array.
The new proposal provides the following Bill of Materials (BOM):
– HP StoreSure 2000 – 155 TB of Midline SAS SFF Drives – FC Controller Pair
– A pair of HP SN6000B 16Gb 48-port/48-port Active Fibre Channel switches
– HP P2000 Remote Snap Software
– HP SN1000 2 Port 16 Gb HBAs
– 24 Fibre Channel cables
– 10 HP ProLiant DL360 Gen8s
– vSphere Enterprise Plus and vCenter licenses from HP
– Call-to-repair 24×7 coverage with four-hour on-site response
The customer operating budget is constrained, and the price of the BOM is too high.
Which components do you propose to change to meet their budget goals without sacrificing their
critical to quality goals? (Select two.)